SPCS School Bond Update
As you may know, the school bond issue passed back in May 2020. These bonds will provide a new Springfield Elementary School building and additions and improvements to Westmont Elementary School. These plans will increase security, provide adequate learning spaces, improve infrastructure, add room for growth, and more. You will begin to see more changes this month and into the summer. Included below is a current timeline for each school building project.
Westmont Elementary Upcoming Milestone Dates
- Construction kick-off meeting - Took place in February
- Mobilize on-site (job site trailer, temp fence, etc.) - Week of February 15
- Start demolition and earthwork - Week of February 22
- Sanitary sewer shutdown/reconnect - Week of March 15
- Install temp partition and start work in existing preschool classroom - Week of March 15
- Start footings for the addition - Week of March 22
- Anticipated job completion date - February 2022
- Construction has begun at Westmont Elementary School. We apologize for any inconveniences due to limited parking around the school. Thank you for your patience and understanding.



Springfield Elementary Upcoming Milestone Dates
- Construction kick-off meeting - Took place in February
- Mobilize on-site (job site trailer, temp fence, etc.) - Week of March 1
- Start building pad and site prep - Week of March 15
- Start footings - Week of April 5
- Anticipated job completion date - July 2022
Each school is communicating any changes (i.e., parking lot plans) with their community members. If you have any questions, please feel free to contact your school's principal or contact Nichole Baugh by email.